Lorne Street Storm Water Mitigation Project Phase III Update July 5

Quarry work is complete, Crescent Street almost finished.

Installation of the water control structure at the Pickard Quarry and final site work is complete. Originally scheduled to take until August to construct, Beale & Inch completed the work last week. Once again, we appreciate the cooperation from Quarry Lane residents during construction.

Beale & Inch are close to completing the work at Crescent Street. The underground infrastructure is in place and the crew is working on the ditching between Crescent Street and the aboiteau. If the weather cooperates, this will be finished in the next couple of weeks, and Beale & Inch will move their team to Sloan Street. Drivers are asked to please respect the closed road signs while construction is ongoing.